787 Schedule Hinges On Fire Investigation







By Guy Norris

Depending on the outcome of investigations into the Nov. 9 Boeing 787 electrical fire, Boeing’s hard-pressed certification and delivery schedule could face worst-case-scenario delays of up to 10 months, says aerospace analysts.

Morgan Stanley Research speculates that in the most extreme case, if Boeing is required to undertake major redesign, testing and certification of the electrical system, ...