|

Boeing shakes off tough year for 747-8 .

Click here for more news / Clique aqui para mais notícias


By Stephen Trimble

Veteran Boeing programme executive Mohammed "Mo" Yahyavi inherited the 747-8 programme in February as development of the next-generation widebody was still emerging from under a cloud of delays and cost overruns.

Coming only three months after Boeing chief executive Jim McNerney expressed "frustration" with 747-8 issues, leading to widespread doubts about Boeing's support for the programme, Yahyavi appeared to be facing a classic turnaround situation.

Perhaps surprisingly, Yahyavi, an Iranian-born and Italian navy-trained engineer, says that he arrived at the 747-8 programme in February to find a fundamentally solid plan for development and production, and a strong staff already in place to carry it out.

747-8 (445)
© Boeing

"I saw a very strong capable team in place," Yahyavi says. "This is a very important programme for the company and industry, so there has been a really good focus at the programme level with all aspects of best practices in place.

"It came to me very quickly that I did not really need to change anything," he adds. "I believed I could follow this process already in place and act like a cheerleader and get the team going."

Yahyavi's public confidence for the 747-8's existing plans and team marked a major mood reversal within the development programme.

After all, within the past 10 months, the 747-8 has endured two announced schedule delays, its second unexpected leadership change and a confidence crisis sparked by an equivocating remark by McNerney in January about Boeing's commitment to the programme.

After a four-year marketing effort, the 747-8 Intercontinental has attracted only a single firm order from a commercial customer with 20 aircraft ordered by Lufthansa Airlines.

Asked by an analyst in January if Boeing could cancel the slow-selling 747-8I, McNerney replied: "We still see a viable business proposition here. Now obviously if we ever got to a point where we didn't, we'd have to work with our customers to come up with another answer."

Boeing's communications staff quickly followed up to clarify that the company remains solidly behind the 747-8I programme.

Since McNerney's remarks in January, the 747-8I design team has also continued to make progress. As of late May, the company had completed about one-third of the engineering design drawings required to start the building process.

Moreover, Yahyavi expresses an unwavering confidence for the future of the 747-8I, which is now not expected to enter service until the third quarter of 2011.

"We are fully, fully committed, dedicated and invested in this product," Yahyavi says. "Absolutely, there is no doubt in my mind. I have the full support of the company. I have no shortages as far as parts or resources. Everything is in place."

In early May, a Bloomberg reporter quoted Yahyavi confidently predicting that Boeing would sign a new order for 747-8Is in the near future. Asked about the comments a few weeks later, Yayhavi would only say that he is "optimistic" about the possibility of new orders.

"We are engaged in very active discussions with several airlines about this airplane," he says, adding that the airlines want to "understand more about" the aircraft.

The market is also waiting to know more about the 747-8 Freighter, the first of the two variants scheduled to enter service. The first components of the aircraft began arriving in August at Boeing's final assembly plant in Everett, Washington. As the sections and parts began arriving, Boeing realised its production system had failed to keep pace with design changes. The programme, then led by Ross Bogue, began a review of the production system that concluded the delivery schedule was unrealistic.

In the midst of the production review, Boeing also faced a 57-day labour strike called on 6 September by the International Association of Machinists and Aerospace Workers (IAM).

By mid-November, the workers had returned to the final assembly line. Boeing, however, was forced to announce a delay of up to nine months for the 747-8F, now scheduled for the third quarter of 2010. The 747-8I's first delivery slipped from late 2010 to the second quarter of 2011. In April, Boeing's decision to slow the delivery rate for 747-8Fs also meant that the first 747-8I delivery would be delayed again to the third quarter of 2011.

Despite the production breakdowns, Yahyavi says the programme is still on track to achieve first flight by the end of the year. The programme has completed assembly of the 27.2m (89ft) forward fuselage section, including the upper-deck. That section has also been moved from the final assembly installation tool for sealing and testing before starting the systems installation process.

"On the first airplane we are almost about halfway to completion of assembly," Yahyavi says. All of the major fuselage sections for airplane 1 are at the Everett plant. The first aircraft's wing has also been completed, including the struts and pylons for the General Electric GEnx-2b engines.

Meanwhile, GE's 747-100 Flying Testbed based in Victorville, California is about halfway complete on certification tests for the aircraft's conventional bleed-air propulsion systems, Yahyavi says.

Further, the fuselage sections for airplanes 2 and 3, which comprise the flight-test fleet, are also in work on the final assembly line.

"We want obviously these airplanes to come together in a certain period of time so we can have a very efficient and quick flight test," Yahyavi says.

Yahyavi also estimates that the time between first flight of the 747-8F and delivery to launch customer Cargolux will span 10-11 months. The scheduled delivery window for the third quarter of 2010 ends on 30 September, meaning that first flight must be before 30 November for Boeing to meet its current schedule.

At the same time, the status of the air cargo market has dramatically declined with the ongoing global economic crisis. The worsening financial outlook for the 747-8F's customers has not yet translated into lost orders for Boeing.

"We have no cancellations on the freighter," Yahyavi says. "All of our customers love the airplane, they want to stay with the airplane."

Boeing decided in April to slow production output for all of its widebodies except the 787. That change allowed Boeing to adjust its delivery schedule so that it aligned with the recent demands of its customers, including on the 747-8F line. "There is no doubt the freighter market is soft and we are working directly with every single customer to accommodate their plan and their schedule," he says.

In addition to the slower output off the production line, Boeing has also received requests from 747-8F customers to defer some delivery slots, allowing some customers to move ahead, Yayhavi says.

However, the opportunity created by the deferrals will not lead to changes in the 747-8I schedule. Those customers - either Lufthansa or VIP configuration buyers - will not be able to receive any aircraft earlier than the current scheduled delivery in the third quarter of 2011, Yayhavi says. "That is not in our plan right now," he adds.

Boeing is also making progress on its weight reduction plan for the 747-8F. Last year, Bogue disclosed that the 747-8 exceeded its weight target by at least 1%. With the freighter design about 98-99% complete, Yahyavi says "we have some weight challenges there. But it's not huge."

The programme is looking at all opportunities to remove weight from the aircraft, he adds, to include the fuselage and propulsion system. As a sign of progress, the fourth aircraft in production beat the weight its predecessor in final assembly.





◄ Share this news!

Bookmark and Share

Advertisement







The Manhattan Reporter

Recently Added

Recently Commented