|

French Aim To Push Compromise On A400M

Feb 12, 2009
By Michael A. Taverna




PARIS – France appears ready to pull out all the stops to convince partners that they should agree to renegotiate price, delivery terms and specifications for the A400M, and not stop the troubled multibillion euro initiative.

Meeting with reporters here Feb 10, the chairmen of the French Senate’s foreign affairs, defense and armed forces and finance committees presented a report confirming Airbus warnings last month that the airlifter program could be up to four years late. Combined with indications that the A400M might not meet certain design specifications, notably with respect to weight, the warnings are pushing some partners, in particular the U.K., to threaten to pull out.

Seven European countries have ordered a total of 180 A400Ms, led by Germany (60), France (50), Spain (27) and the U.K. (25).

Delivery of the digital engine control system (FADEC), recently programmed for July, is now expected around October. This means the A400M is unlikely to make its first flight until early 2010 – two years behind the original schedule. Initial deliveries are not expected until late 2012, and perhaps late 2013 – four years later than called for – if the prime contractor, Airbus, decides to limit production in the first year to allow for maturing design.

Nevertheless, the chairmen said findings indicated that management reshuffles inside EADS/Airbus and within the propulsion team – with Rolls-Royce and Snecma now assuming a lead role – can get the program back on track and that technical hurdles are not insurmountable. EADS officials suggested additional benefit could be realized by separating development of the propulsion system into a separate contract, distinct from that of the aircraft system.

French press reports suggest fixing the program could raise its cost by 5 billion euros ($6.5 billion), the amount that customers have paid out to date for the 20 billion euro undertaking. EADS has provisioned 1.8 billion euros so far for schedule and cost overruns, with lesser amounts coming from other contractors.

But the lawmakers also suggested that abandoning the effort – Europe’s biggest cooperative military undertaking by far – would entail an economic, financial and political cost far outweighing the cost of setting it right. They said they had submitted their findings directly to French President Nicolas Sarkozy with the request that the matter be brought up at the highest political level as soon as European defense procurement agency Occar, which is managing the A400M, finishes its ongoing inquiry into program difficulties. This is expected within a few weeks.

Under the terms of the contract, the seven launch customers can pull out of the deal or seek to renegotiate its terms if delivery is delayed more than 14 months. This provision becomes effective on March 31.

Committee member Jacques Gautier said France will be forced to resort to various stratagems to meet its own interim airlift needs until the A400M is ready. Among these are to prolong the life of some of its Transalls, where possible; pushing forward the acquisition of two A330s due to be purchased under a forthcoming tanker-transport buy; wet-leasing more An-124s; and acquiring a few Casa C212/235 light transports. Leasing a few Lockheed Martin C130Js or Boeing C-17s is also “not excluded,” he says, “as long as it does not threaten the future of the A400M.”

Photo: Airbus Military




◄ Share this news!

Bookmark and Share

Advertisement







The Manhattan Reporter

Recently Added

Recently Commented